Disaster Recovery Funding Arrangements (DRFA) - Submission overview
On this page:
About
This guidance provides local governments and state agencies a quick overview of standard joint Commonwealth/State funded funding relief measures that may be activated as assistance towards the cost of responding to, and recovering from eligible disasters.
Counter Disaster Operations (CDO)
| CDO Details | Counter Disaster Operations |
|---|---|
| Description | CDO activities are activities undertaken by local governments and state agencies responding to a disaster event to:
|
| Detailed requirements | |
| CDO funding readiness | Are your systems and processes ready before a disaster occurs to meet the CDO requirements and track costs and activities to each disaster event? CDO submissions must be lodged as claims for the reimbursement of actual extraordinary costs of CDO activities completed within a financial year (FY), in direct response to each eligible disaster. |
| Eligible timeframes | CDO activities must be completed:
|
| Submission requirements | Use the CDO Submission form and the QDFG guidelines to ensure your systems and processes are ready to collect the required data and evidence as you deliver CDO activities, including:
|
| Due date for lodging claims | Submissions are to be lodged within three months from end of FY in which the CDO activities were completed (i.e. by 30 September), regardless of when the invoice was paid. |
| Approval and payment |
|
| Reporting | To inform QRA’s annual acquittal of DRFA funding to the Commonwealth, CDO activated councils and state agencies will be asked to report on the anticipated number and value of CDO submissions to be lodged. |
| Reference and tools |
|
| Need Help? | Contact your Contact your QRA Regional Liaison Officer (RLO) |
Emergency Works (EWK)
| EWK Details | Emergency Works |
|---|---|
| Description | Emergency Works (EWK) funding is activated under Reconstruction of Essential Public Assets (REPA). A council’s estimated cost of damage to eligible assets must exceed its trigger point to be eligible to activate or apply for REPA, EWK or Immediate Reconstruction Works funding. EWK are temporary works completed by councils & state agencies to:
|
| Detailed requirements | QDFG Section 4, Activation process and Section 9, relief measures for essential public assets DRFA 2018 and Guideline 1 Essential Public Asset |
| EWK funding readiness | Are your systems and processes ready before a disaster occurs to meet the EWK requirements and track costs to the emergency works you complete on assets that have been impacted by a future disaster event? Are you ready to gather the required data, post event damage photos and financial evidence while you are undertaking the emergency works? EWK submissions must be lodged as claims for the reimbursement of actual costs of emergency works completed within a financial year (FY) in direct response to each eligible disaster event. Refer to QRA’s pre-season checklist |
| Eligible timeframes | Emergency works:
|
| Submission requirements | Use the EWK Submission form and the QDFG to ensure your systems and processes are ready to collect the required post event photos, data and evidence as you deliver emergency works. Requirements include:
|
| Due date for lodging claims | EWK submissions are to be lodged within three months from end of FY in which the emergency works were started and completed (i.e. by 30 September), regardless of when the invoice was paid. Where works commence late in FY and are completed early the following FY, submissions are to be lodged by 30 October of the FY in which the works were completed. |
| Approval and payment |
|
| Reporting | To inform QRA’s reporting of DRFA funding to the Commonwealth, REPA activated councils and state agencies will be asked to report to QRA on anticipated number and value of EWK, IRW and REPA submissions to be lodged. |
| Reference and tools |
|
| Need help? | Contact your Contact your QRA Regional Liaison Officer (RLO) |
Immediate Reconstruction Works (IRW)
| IRW Details | Immediate Reconstruction Works |
|---|---|
| Description | Reconstruction Works (IRW) funding is activated under REPA. A council’s estimated damage costs to eligible assets must exceed its trigger point to be eligible to request activation of and apply for funding under DRFA REPA, EWK or IRW. IRW is the scope of reconstruction works completed by local government and state agencies to urgently and permanently reconstruct an eligible essential public asset to pre-disaster function, where no further REPA works are required at the asset site. |
| Detailed requirements |
|
| IRW funding readiness | Are your systems and processes ready before a disaster occurs to meet the IRW requirements? Is your Digital Road Network data up to date in your and QRA’s systems? Before commencing any immediate reconstruction works are your systems and people ready to gather the required pre and post event evidence and asset location data, track costs to the scope, plus photo evidence demonstrating the completed works? IRW submissions must be lodged as claims for reimbursement of the actual costs of a detailed scope of works completed to reconstruct an eligible asset damaged by an eligible disaster. Refer to QRA’s pre-season checklist |
| Eligible timeframes |
|
| Submission requirements | Use the IRW Submission form, QDFG and QRA Treatment Guide to ensure your systems and processes are ready to collect the required photos, data and evidence as you scope, plan, cost and deliver IRW works. Submission requirements include:
|
| Due dates for lodging submissions | Submissions are to be lodged within three months from the end of the FY in which the works commenced (by 30 September). Where eligible works fall across two financial years (i.e. commence late one FY and completed early the following FY) the submission is to include all expenditure for the works completed up to 30 September, and should be lodged as soon as practicable as agreed with QRA. |
| Approval and payment |
|
| Reporting | REPA activated local governments and state agencies are required to report to QRA on anticipated number and value of EWK, IRW and REPA submissions to be lodged. |
| Reference and tools |
|
| Need help? | Contact your QRA Regional Liaison Officer (RLO) |
Reconstruction of Essential Public Assets (REPA)
| REPA Details | Reconstruction of Essential Assets |
|---|---|
| Description | Reconstruction of Essential Public Assets (REPA) refers to the permanent reconstruction works for an essential public asset that has been directly damaged by an eligible disaster. An essential public asset directly damaged by an eligible disaster, or a redamaged essential public asset may be reconstructed to its pre-disaster function. |
| Detailed requirements |
|
| REPA funding readiness | Are your systems and processes ready before a disaster occurs to meet the REPA requirements? Is your Digital Road Network data up to date in your and QRA’s systems? Before commencing any reconstruction works are your systems and people ready to gather the required pre and post event evidence and asset location data, track costs to the scope, plus photo evidence demonstrating the completed works? Refer to QRA’s pre-season checklist |
| Eligible timeframes | Post event damage assessments & geo tagged photo evidence must be collected within 12 months after the eligible disaster, or within nine months (by 31 March) following the FY in which the disaster occurred Pre-disaster asset condition evidence: date collected may be up to four years prior to the event (local governments or up to two years prior to the event (state agencies). Lodgement due date: All REPA scope and tendered market prices must be lodged within nine months (by 31 March) following the FY in which the disaster occurred. Note – this includes lodging Estimate Updates (EU) to vary approved submissions’ scope or market price values. Completion timeframe: All approved REPA submission works must be completed within 24 months after the end of the FY in which the disaster occurred. Acquittal due date: All REPA close-out submissions and completion evidence are to be lodged within three months following the FY (i.e. by September 30) in which works were completed. |
| Submission requirements | Use the REPA Submission form, QDFG and QRA Treatment Guide to ensure your systems and processes are ready to undertake post event damage assessments, build scope and lodge submissions that meet the DRFA requirements. This includes:
|
| Due dates for lodging submissions | Lodgement due date - All REPA submissions, including the proposed scope of works and the awarded market prices, must be lodged with QRA within nine months (by 31 March) following the financial year in which the disaster occurred (unless otherwise directed by QRA). |
| Approval and payment |
|
| Reporting | Monthly progress reporting on REPA scope, costs and timeframes is mandatory throughout delivery (refer 9.5.6 Progress reporting and progress claims). REPA Close-out requirements: Applicants must lodge a Final Progress Report supported by evidence of expenditure (detailed general ledger, payroll report) and a detailed close out submission line item data, reasons for variances, and photo evidence demonstrating the completed scope of works. Timesheets, invoices etc must be available for sampling. |
| Reference and tools |
|
| Need help? | Contact your QRA Regional Liaison Officer (RLO) |
Print version PDF
QRA Reference: DOC/18/24065.